Next stages of road investment implementation in Łódzkie voivodeship start this week

fot. 123rf
A1: Work has started in the sections Tuszyn – Piotrków Trybunalski and Radomsko – voivodeship border

A1: Work has started in the sections Tuszyn – Piotrków Trybunalski and Radomsko – voivodeship border

On Monday, 18th March, work started in two sections of A1 motorway: in “A” section from Tuszyn junction to Piotrków Trybunalski Południe junction (the old section of A1 motorway) and in “D” section from Radomsko to the border of Silesian voivodeship.

Section A (from Tuszyn to Piotrków Trybunalski junction - 15.9 km) for PLN 478.9 million gross will be built by the consortium of companies Budimex - Strabag. The same companies are going to build section C (from Kamieńsk junction to Radomsko junction - 16.7 km), for PLN 573.1 mln gross, while section D (from Radomsko to the border of Silesian voivodeship - 7 km) for PLN 338.25 mln gross is going to be implemented by PUT Intercor.

What is important, the principle was adopted that traffic along the main route (A1, DK1) will not be interrupted during the works.

You can read more about the change in traffic arrangement on the website of the General Directorate for National Roads and Motorways (GDDKiA): https://www.gddkia.gov.pl/pl/a/32649/Wkrotce-ruszaja-praca-budowlane-na-autostradzie-A1-i-DK-91-w-Lodzkiem

A1: The contractor of section Piotrków Trybunalski – Kamieńsk selected

The contractor of section Piotrków Trybunalski – Kamieńsk (“B” section of 25 km) has also been selected. The offer of Mirbud S.A. was considered the most advantageous one. The contractor is going to have 35 months to implement the project, including 10 months for the design and the remaining time for construction works. The contract value amounts to PLN 857 mln.

The most advantageous offer for supervision over this section has also been chosen. The offer was submitted by the consortium of companies: Drogowa Trasa Średnicowa from Katowice and INCO Consulting from Pszczyna. The price of the offer amounts to almost PLN 14.1 mln.

Contract signed with the contractor of technical concept for extension of A2 motorway with the third lane

In March, the General Directorate for National Roads and Motorways in Łódź signed a contract with the contractor of the technical concept necessary to obtain the environmental approval of extension of A2 motorway with the third lane in Łódź section.

The technical concept for extension of A2 motorway with the third lane from Łódź-Północ junction to the border with Mazowieckie voivodeship will be prepared for PLN 2.48 mln gross by the company Transprojekt Gdański.

This is the first stage of implementation of the investment involving the extension of one of the most important transport routes in the country in the east-west direction, estimated to amount to approx. PLN 600 mln.